Abstract: Project acceleration often results in claims. A LISP program for performing time impact analysis for project acceleration is presented. The program helps the user identify the number of days by which the project can be accelerated and what the user's share will be of the acceleration costs involved. The program analyzes the as‐planned, as‐built, and utility data files submitted by the user and identifies all delayed, accelerated, added, and canceled (DAAC) activities. It then generates as‐planned, as‐built, projected, adjusted, owner‐accountable, and contractor‐accountable schedules. The program performs a compression analysis on the remaining portion of the project. After a consultation session with the user, it apportions acceleration costs between the owner and the contractor in an equitable way. This program is expected to help settle claims.